Which two things should the Development Team do during the first Sprint? (Choose two.)

A.
Make up a plan for the rest of the project.
Answers
A.
Make up a plan for the rest of the project.
B.
Analyze, describe, and document the requirements for the subsequent Sprints.
Answers
B.
Analyze, describe, and document the requirements for the subsequent Sprints.
C.
Develop at least one piece of functionality.
Answers
C.
Develop at least one piece of functionality.
D.
Analyze, design, and describe the complete architecture and infrastructure.
Answers
D.
Analyze, design, and describe the complete architecture and infrastructure.
E.
Create an increment of potentially releasable software.
Answers
E.
Create an increment of potentially releasable software.
Suggested answer: C, E