Question 92 - PSM I discussion
Which two activities will a Product Owner engage in during a Sprint? (Choose the best two answers.)
A.
Run the Daily Scrum.
B.
Prioritize the Development Team's work on the Sprint Backlog.
C.
Update the Sprint burndown chart.
D.
Answer questions from the Development Team about items in the current Sprint.
E.
Work with the stakeholders.
Your answer: