Question 102 - PSM I discussion
When should a Sprint Goal be created? (Choose the best answer.)
A.
It should have been created in the previous Sprint during Product Backlog refinement.
B.
It must be established before Sprint Planning in order to begin planning.
C.
A Sprint Goal is not mandatory in Scrum.
D.
At any time during the Sprint.
E.
During Sprint Planning.