As the Development Team starts work during the Sprint, it realizes it has selected too much work to finish in the Sprint. What should it do? (Choose the best answer.)
A.
Inform the Product Owner at the Sprint Review, but prior to the demonstration.
B.
Find another Scrum Team to give the excess work to.
C.
As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.
D.
Reduce the definition of "Done" and get all of the Product Backlog items "Done" by the new definition.