A Sprint Retrospective should be held: (Choose the best answer.)

A.
At the end of each Sprint.
Answers
A.
At the end of each Sprint.
B.
At the beginning of each Sprint.
Answers
B.
At the beginning of each Sprint.
C.
Only when the Scrum Team determines it needs one.
Answers
C.
Only when the Scrum Team determines it needs one.
D.
At the end of the last Sprint in a project or a release.
Answers
D.
At the end of the last Sprint in a project or a release.
Suggested answer: A