When is implementation of a Product Backlog item considered complete? (Choose the best answer)

A.
At the end of the Sprint.
Answers
A.
At the end of the Sprint.
B.
When the item has no work remaining in order to be potentially released.
Answers
B.
When the item has no work remaining in order to be potentially released.
C.
When Quality Assurance reports that the item passes all acceptance criteria.
Answers
C.
When Quality Assurance reports that the item passes all acceptance criteria.
D.
When all work in the Sprint Backlog related to the item is finished.
Answers
D.
When all work in the Sprint Backlog related to the item is finished.
Suggested answer: B