When does the second Sprint start? (Choose the best answer.)

A.
Once the architectural changes for the second Sprint have been approved by the senior architect.
Answers
A.
Once the architectural changes for the second Sprint have been approved by the senior architect.
B.
After the Product Backlog for the second Sprint has been selected.
Answers
B.
After the Product Backlog for the second Sprint has been selected.
C.
Immediately after the first Sprint.
Answers
C.
Immediately after the first Sprint.
D.
After the customer completes acceptance testing of the first Sprint.
Answers
D.
After the customer completes acceptance testing of the first Sprint.
Suggested answer: C