Scrum PSM I Practice Test - Questions Answers, Page 16
List of questions
Question 151
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which are NOT appropriate topics for discussion in a Sprint Retrospective? (Choose two.)
Definition of "Done".
How the team does its work.
Team relations.
The value of work currently represented in the Product Backlog.
Arranging the Sprint Backlog for the next Sprint.
Suggested answer: D, E
Question 152
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?
There are no such activities. The next Sprint starts immediately after the current Sprint.
Refine the Product Backlog.
Work with the Quality Assurance departments on the Increment of the current Sprint.
Update the project plan with stakeholders.
Suggested answer: A
Question 153
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Who is on the Scrum Team? (Choose three.)
Scrum Master
Product Owner
Development Team member
Project Manager
None of the above
Suggested answer: A, B, C
Question 154
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which of the following are roles on a Scrum Team? (Choose three.)
Users
Scrum Master
Product Owner
Development Team
Customers
Suggested answer: B, C, D
Question 155
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which does a self-organizing Development Team choose?
Sprint length.
How to best accomplish its work.
Stakeholders for the Sprint Review.
When to release, based on its progress.
Product Backlog ordering.
Suggested answer: B
Question 156
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A Scrum Team is only allowed to meet with stakeholders during Sprint Review.
True
False
Suggested answer: B
Question 157
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Why is the Daily Scrum held at the same time and same place?
The consistency reduces complexity.
The place can be named.
The Product Owner demands it.
Rooms are hard to book and this lets it be booked in advance.
Suggested answer: A
Question 158
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which best describes the Product Backlog?
It is allowed to grow and change as more is learned about the product and its customers.
It provides just enough information to enable a Scrum team to start the design phase of a product.
It contains all foreseeable tasks and requirements from which the Scrum team can develop and maintain a complete project plan.
It is baselined to follow change management processes.
Suggested answer: A
Question 159
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum? (Choose two.)
A shared understanding of the most important work to be undertaken next to achieve the best possible progress toward the Sprint goal.
An update of completed tasks and of the remaining work so the Scrum Master can plan the next day.
A status report for the upper management indicating what each individual has done, will be doing, and what is impending him/her.
An updated Scrum board to make Sprint progress transparent for the stakeholders.
New impediments for the Scrum Master to take care of.
Suggested answer: A, E
Question 160
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Who has the final say on the order of the Product Backlog?
The Development Team.
The Product Owner.
The Scrum Master.
The Stakeholders.
The CEO.
Suggested answer: B
Question