When does the next Sprint begin?

A.
When the Product Owner is ready.
Answers
A.
When the Product Owner is ready.
B.
Immediately after the conclusion of the previous Sprint.
Answers
B.
Immediately after the conclusion of the previous Sprint.
C.
The Monday following the Sprint Review.
Answers
C.
The Monday following the Sprint Review.
D.
Immediately following the next Sprint Planning.
Answers
D.
Immediately following the next Sprint Planning.
Suggested answer: B