The IT manager asks a Development Team for a status report describing the progress throughout the Sprint. The Development Team asks the Scrum Master for advice. The Scrum Master should:

(Choose the best answer.)

A.
Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.
Answers
A.
Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.
B.
Tell the Development Team to figure it out themselves.
Answers
B.
Tell the Development Team to figure it out themselves.
C.
Tell the Development Team to fit the report into the Sprint Backlog.
Answers
C.
Tell the Development Team to fit the report into the Sprint Backlog.
D.
Create and deliver the report to the manager herself.
Answers
D.
Create and deliver the report to the manager herself.
E.
Ask the Product Owner to send the manager the report.
Answers
E.
Ask the Product Owner to send the manager the report.
Suggested answer: A