List of questions
Related questions
Question 206 - PSM I discussion
When does a Developer become accountable for an item in the sprint Backlog?
(choose the best answer)
A.
During the Daily Scrum
B.
Never am Developers on the Scrum Team share accountability tor items in the
C.
As soon as a Developer on the Scrum Team can accommodate more work
D.
At Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers
Your answer:
0 comments
Sorted by
Leave a comment first