When must a scrum Team release each increment? (choose the best answer)

A.
when the Scrum Team finishes their work
Answers
A.
when the Scrum Team finishes their work
B.
Alter every Sprint. without exception
Answers
B.
Alter every Sprint. without exception
C.
Whenever the product s tree of detects
Answers
C.
Whenever the product s tree of detects
D.
When it makes sense to release It.
Answers
D.
When it makes sense to release It.
Suggested answer: D

Explanation:

According to the Scrum Guide, a Scrum Team must release each Increment when it makes sense to do so, based on the value and feedback obtained from stakeholders. The decision to release an Increment is made by the Product Owner, who is responsible for maximizing the value of the product and the work of the Development Team. The other options are not valid, as they imply that releasing an Increment is either mandatory (such as after every Sprint), conditional (such as when the product is free of defects), or irrelevant (such as when the Scrum Team finishes their work).