One of the Scrum events is the Daily Scrum. What are two intended outcomes ot the Daily Scrum?
(choose the best two answers)
A.
An updated Scrum board to make Sprint progress transparent for the stakeholders
B.
Identification of impediments that may prevent the Developers from achieving the Sprint Goal.
C.
A status report tor the upper management indicating what each individual has done, will be doing, and what is impeding him/her.
D.
A shared understanding ot the most important work to be undertaken next to achieve the best possible progress toward the Sprint goal.
E.
An update of completed tasks and ot the remaining work so the Scrum Master can plan the next day.