Which four of the following risks to product development are addressed by Scrum?
(choose the best four answers)
A.
The timescale of the planned work.
B.
The stability and complexity of the technology.
C.
The complexity and unpredictability of the requirements.
D.
The skills and working relationships of the people on the teams.
E.
The definition of incentive and bonus strategies by Human Resources for all team members.
F.
The clear definitions of stages and gateways in the overall governance model.