Which four of the following risks to product development are addressed by Scrum?

(choose the best four answers)

A.
The timescale of the planned work.
Answers
A.
The timescale of the planned work.
B.
The stability and complexity of the technology.
Answers
B.
The stability and complexity of the technology.
C.
The complexity and unpredictability of the requirements.
Answers
C.
The complexity and unpredictability of the requirements.
D.
The skills and working relationships of the people on the teams.
Answers
D.
The skills and working relationships of the people on the teams.
E.
The definition of incentive and bonus strategies by Human Resources for all team members.
Answers
E.
The definition of incentive and bonus strategies by Human Resources for all team members.
F.
The clear definitions of stages and gateways in the overall governance model.
Answers
F.
The clear definitions of stages and gateways in the overall governance model.
Suggested answer: A, B, C, D

Explanation:

Scrum is a framework for addressing complex adaptive problems, such as product development, that require empirical process control and frequent inspection and adaptation. Scrum helps to mitigate the risks of:

The timescale of the planned work (A), by delivering potentially releasable increments of value at the end of each Sprint, which is a fixed time-box of one month or less.

The stability and complexity of the technology (B), by allowing the Development Team to self-organize and choose the best way to create a ''Done'' increment that meets the Definition of Done.

The complexity and unpredictability of the requirements , by enabling the Product Owner to manage the Product Backlog, which is an ordered list of what is needed in the product and can change as more is learned about the product, users, market, and technology.

The skills and working relationships of the people on the teams (D), by fostering a culture of collaboration, transparency, and accountability among the Scrum Team members and stakeholders.