The timebox for the Sprint Review is:

(choose the best answer)

A.
Any length of time needed.
Answers
A.
Any length of time needed.
B.
At the end of every Sprint.
Answers
B.
At the end of every Sprint.
C.
15 minutes.
Answers
C.
15 minutes.
D.
4 hours for a 4-week Sprint. Usually shorter for shorter Sprints.
Answers
D.
4 hours for a 4-week Sprint. Usually shorter for shorter Sprints.
Suggested answer: D

Explanation:

D is correct because the timebox for the Sprint Review is four hours or less for a one-month Sprint, and usually shorter for shorter Sprints1.The Sprint Review is an event where the Scrum Team and the stakeholders inspect the outcome of the Sprint and collaborate on what to do next1.A is incorrect because the Sprint Review is not an open-ended event, but a timeboxed one that respects the attendees' time and ensures productivity2.B is incorrect because the Sprint Review is not a point in time, but a timeboxed event that has a specific purpose and agenda1.C is incorrect because the Sprint Review is not the same as the Daily Scrum, which is a 15-minute event for the Developers to synchronize their work1.