Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

A.
Approving the change request
Answers
A.
Approving the change request
B.
Developing a rollback plan
Answers
B.
Developing a rollback plan
C.
Gathering necessary resources
Answers
C.
Gathering necessary resources
D.
Defining requirements
Answers
D.
Defining requirements
Suggested answer: B

Explanation:

When implementing an IT infrastructure change that takes risks into consideration, the project manager should develop a rollback plan. A rollback plan is a contingency plan that outlines the steps that need to be taken in case the change does not work as expected. It includes a plan to roll back the changes and restore the system to its previous state. Reference: CompTIA Project+ Study Guide

Section 3.3.

The project manager should develop a rollback plan when implementing an IT infrastructure change that takes risks into consideration. A rollback plan is a contingency plan that describes how to revert back to the previous state of the system in case of a failure or disruption during the change implementation. A rollback plan can help to minimize the impact of the change on the system performance and availability and ensure business continuity and data integrity.