A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

A.
ESG
Answers
A.
ESG
B.
PHI
Answers
B.
PHI
C.
Pll
Answers
C.
Pll
D.
ROI
Answers
D.
ROI
Suggested answer: A

Explanation:

The project manager should have considered environmental, social, and governance (ESG) factors during initial planning to prevent the situation of receiving a penalty for disposing of some computers improperly. ESG factors are criteria that measure the sustainability and ethical impact of an organization's activities. They include aspects such as environmental protection, social responsibility, human rights, diversity, and corporate governance. Considering ESG factors can help to reduce risks, improve reputation, and enhance performance of an organization12

asked 02/10/2024
megat ilham
35 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first