Question 20 - PK0-005 discussion
Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?
A.
Project change management plan
B.
Project management plan
C.
Project transition plan
D.
Project communication plan