Question 23 - PK0-005 discussion
In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?
A.
Assemble a new project with existing resources.
B.
Obtain the final report from release management.
C.
Notify the functional manager that resources are released.
D.
Allocate resources in a different project