A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?
A.
Time and materials contract
B.
Master service agreement
C.
Fixed-price contract
D.
Statement of work
E.
Cost-plus agreement