ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 24 - PK0-005 discussion

Report
Export

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

A.
Time and materials contract
Answers
A.
Time and materials contract
B.
Master service agreement
Answers
B.
Master service agreement
C.
Fixed-price contract
Answers
C.
Fixed-price contract
D.
Statement of work
Answers
D.
Statement of work
E.
Cost-plus agreement
Answers
E.
Cost-plus agreement
Suggested answer: A

Explanation:

The project manager should put in place a time and materials contract before work begins for a third party that needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. A time and materials contract is a type of contract where the buyer pays the seller based on the actual time spent and materials used during the project. A time and materials contract is suitable for projects that have uncertain or variable scope, duration, or cost. A time and materials contract can provide flexibility and adaptability for both parties and allow them to adjust to changing requirements or circumstances.

asked 02/10/2024
Marc Casin Martinez
41 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first