Question 103 - PK0-005 discussion
A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources. Which of the following risk responses does this demonstrate?
A.
Avoid
B.
Transfer
C.
Accept
D.
Share