After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

A.
Continuous integration
Answers
A.
Continuous integration
B.
Rollback plan
Answers
B.
Rollback plan
C.
Customer notification
Answers
C.
Customer notification
D.
Automated testing
Answers
D.
Automated testing
Suggested answer: C

Explanation:

Customer notification should be added to the issue log after receiving an escalation from an executive about the extension of the downtime after the scheduled window. Customer notification is a communication activity that informs the customers about any issues or changes that may affect their satisfaction or expectations. Customer notification can help to maintain trust, transparency, and goodwill with the customers and prevent any negative impacts on their business operations or experience.