Question 37 - PK0-005 discussion
As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?
A.
Document the request in the change control log.
B.
Communicate the change deployment.
C.
Conduct an impact assessment.
D.
Implement the change.