Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?

A.
Gantt chart
Answers
A.
Gantt chart
B.
Maintenance window schedule
Answers
B.
Maintenance window schedule
C.
Functional requirements
Answers
C.
Functional requirements
D.
Test results
Answers
D.
Test results
Suggested answer: A

Explanation:

The project manager should consult a Gantt chart after the sponsor states that the project is taking too long to complete. A Gantt chart is a graphical tool that shows the schedule of a project, including the start and end dates, durations, dependencies, milestones, and progress of each task or activity. A

Gantt chart can help to monitor and control the project timeline and identify any delays, variances, or issues that may affect the project completion.