Question 43 - PK0-005 discussion
Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?
A.
Gantt chart
B.
Maintenance window schedule
C.
Functional requirements
D.
Test results
Your answer: