After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?

A.
Implement the change.
Answers
A.
Implement the change.
B.
Approve the test plan.
Answers
B.
Approve the test plan.
C.
Notify customers.
Answers
C.
Notify customers.
D.
Develop a rollback plan.
Answers
D.
Develop a rollback plan.
Suggested answer: D

Explanation:

The project manager should develop a rollback plan next after determining the appropriate maintenance window in the operational infrastructure change process. A rollback plan is a contingency plan that describes how to revert to the previous state of the system or infrastructure in case of a failure or disruption during the change implementation. A rollback plan can help to minimize the impact and risk of the change and ensure business continuity and stability.