A project implementation partner and the project manager disagree about completed requirements.
The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?
A.
SOW
B.
RFI
C.
RFQ
D.
WBS