A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

A.
Scope creep
Answers
A.
Scope creep
B.
Collecting requirements
Answers
B.
Collecting requirements
C.
Decision-making
Answers
C.
Decision-making
D.
Project change
Answers
D.
Project change
Suggested answer: A

Explanation:

Scope creep is most likely happening when a key stakeholder recommends to a senior developer that a new feature be added that is not part of the current requirement documentation. Scope creep is a term that refers to the uncontrolled expansion or change of a project's scope beyond its original boundaries or objectives. Scope creep can happen due to various reasons, such as changing customer demands, unclear or incomplete requirements, poor communication, lack of change control, or stakeholder interference. Scope creep can have negative impacts on a project, such as delays, cost overruns, quality issues, or reduced customer satisfaction12