For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

A.
Resource plan
Answers
A.
Resource plan
B.
Organizational chart
Answers
B.
Organizational chart
C.
Project charter
Answers
C.
Project charter
D.
RACI chart
Answers
D.
RACI chart
Suggested answer: D

Explanation:

A RACI chart would be the most useful option for the project manager to illustrate roles for major project activities for an upcoming project kickoff. A RACI chart is a visual representation of a RACI matrix that shows who is responsible, accountable, consulted, and informed for each task or activity in a project using a table format. A RACI chart can help to communicate and document the roles and expectations of each team member and stakeholder for the project and ensure alignment and agreement.