A PM learns about some communication issues with different stakeholders and team members.

Which of the following should the PM do NEXT?

A.
Escalate the communication issues.
Answers
A.
Escalate the communication issues.
B.
Implement a communication platform.
Answers
B.
Implement a communication platform.
C.
Review the communication plan.
Answers
C.
Review the communication plan.
D.
Talk with the head of the PMO.
Answers
D.
Talk with the head of the PMO.
Suggested answer: C

Explanation:

The project manager should review the communication plan after learning about some communication issues with different stakeholders and team members. A communication plan is a document that defines and documents the communication goals, strategies, methods, channels, frequency, roles, and responsibilities for a project. A communication plan can help to facilitate effective and timely communication among all stakeholders involved in a project and avoid confusion, misunderstanding, or conflicts.