To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which a following technique is the project manager utilizing?

A.
Process moving
Answers
A.
Process moving
B.
Brainstorming
Answers
B.
Brainstorming
C.
Interview
Answers
C.
Interview
D.
Focus group
Answers
D.
Focus group
Suggested answer: D

Explanation:

A focus group is a technique that involves bringing together a group of stakeholders and facilitating a discussion to elicit their opinions, needs, and expectations about the project. This technique can help to gather requirements from stakeholders in an interactive and collaborative way1, p. 67