A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?

A.
Milestone
Answers
A.
Milestone
B.
Gantt
Answers
B.
Gantt
C.
Burndown
Answers
C.
Burndown
D.
PERT
Answers
D.
PERT
Suggested answer: A

Explanation:

A milestone chart is the best chart to use to show major accomplishments for key events, because it displays the important deliverables or outcomes of a project along a timeline12.A milestone chart can provide a high-level overview of the project progress and achievements, without showing the details of each task or activity34.A milestone chart can also help communicate the project status and expectations to the stakeholders, and identify any potential risks or delays that may affect the project completion56.Reference= CompTIA Project+ Certification Study Guide7, CompTIA Project+ Certification Exam Objectives8, What is a Milestone Chart?1, How to Create a Milestone Chart in Excel in 3 Steps2, Milestone Chart: The Easiest Way to Track Project Milestones3, How to Use Milestones in Project Management4

asked 02/10/2024
Jason Coleman
39 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first