Question 105 - PK0-005 discussion
During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?
A)
B)
C)
D)
A.
Option A
B.
Option B
C.
Option C
D.
Option D