A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM most likely perform?
A.
Call the previous PM for advice on risks and issues.
B.
Ask the project sponsor to provide previous final project report results.
C.
Complete the project charter using the other PM's subject matter expertise.
D.
Use existing artifacts and accommodate based on the current project success criteria.