A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

A.
Meeting cadence
Answers
A.
Meeting cadence
B.
Gap analysis
Answers
B.
Gap analysis
C.
Dashboard
Answers
C.
Dashboard
D.
Adoption training
Answers
D.
Adoption training
Suggested answer: C

Explanation:

A dashboard is a visual tool that displays key project metrics and indicators in a single view12.A dashboard can help a project sponsor to provide the latest project status information on a weekly executive call by showing the project progress, budget, schedule, risks, issues, and milestones in a clear and concise way34.A dashboard can also facilitate communication, collaboration, and decision making among project stakeholders56.A dashboard should be reviewed and updated regularly to reflect the current state of the project7.Reference= CompTIA Project+ Certification Study Guide8, CompTIA Project+ Certification Exam Objectives9, Write a Project Status Report in 8 Steps + Template [2023] * Asana6, Project Status Reports: 9 Easy Steps & Examples [+ Template]7, How To Write a Project Status Report (Definition and Steps)8, How to Write a Project Status Report [Template Included] - Toggl9, What Is a Project Status?Definition and Key Terms - Indeed10