Question 128 - PK0-005 discussion
Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?
A.
Avoiding
B.
Smoothing
C.
Forcing
D.
Compromising
Your answer: