ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 128 - PK0-005 discussion

Report
Export

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

A.
Avoiding
Answers
A.
Avoiding
B.
Smoothing
Answers
B.
Smoothing
C.
Forcing
Answers
C.
Forcing
D.
Compromising
Answers
D.
Compromising
Suggested answer: A

Explanation:

Avoiding is a conflict resolution technique that involves postponing or withdrawing from a conflict situation. The project manager is using this technique by taking a break and continuing the meeting on another day, hoping that the conflict will resolve itself or become less important over time. This technique may be appropriate when the conflict is trivial, the potential damage is greater than the benefits, or more information is needed before making a decision.Reference=CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 10: Executing and Closing Projects, page 287; [CompTIA Project+ Certification Exam Objectives], Domain 3: Project Execution, Objective 3.2: Given a scenario, apply appropriate conflict resolution techniques.

asked 02/10/2024
JEROME SANANES
40 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first