ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 130 - PK0-005 discussion

Report
Export

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

A.
Schedule
Answers
A.
Schedule
B.
Status report
Answers
B.
Status report
C.
Issue log
Answers
C.
Issue log
D.
Task board
Answers
D.
Task board
Suggested answer: C

Explanation:

An issue log is a document that records and tracks any issues that arise during a project and how they are resolved1.It is different from a risk register, which records and tracks potential risks that may or may not occur during a project2. When a risk becomes an issue, it means that it has occurred and has a negative impact on the project.Therefore, the project manager should update the issue log next to document the compliance issue, its cause, its impact, its priority, its owner, and its resolution status3.Updating the issue log will help the project manager communicate the issue to the stakeholders, monitor the progress of the mitigation plan, and prevent similar issues from happening again4.Reference=CompTIA Project+ PK0-005 Certification Study Guide, Chapter 11: Executing Projects Part 2, page 331;Project Risk Mitigation Guide + Starter Kit | Smartsheet, Risk Register section;How to Make a Risk Management Plan (Template Included) - ProjectManager, Risk Register section;Issue Log - Project Management Knowledge, Introduction section;Issue Log Template: Free Download | ProjectManager, Introduction and How to Use an Issue Log sections.

asked 02/10/2024
Weisi Huang
39 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first