Question 130 - PK0-005 discussion
During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?
A.
Schedule
B.
Status report
C.
Issue log
D.
Task board
Your answer: