A project team member wrote a user guide over the past ten days. Given the following scatter diagram.

Which erf the following can be formally conducted?

A.
The team member prioritized other tasks over the completion of this task
Answers
A.
The team member prioritized other tasks over the completion of this task
B.
The learn member had performance issues over time.
Answers
B.
The learn member had performance issues over time.
C.
There is a negative correlation with 6me and output
Answers
C.
There is a negative correlation with 6me and output
D.
This is a display of units of outstanding work to predict completion
Answers
D.
This is a display of units of outstanding work to predict completion
Suggested answer: C

Explanation:

The scatter diagram shows a clear negative correlation between time (days) and output (pages), meaning as time progresses, the number of pages completed decreases. This is evident from the downward trend of the plotted points on the graph.Reference= CompTIA Project+ Certification Study Guide, Chapter 3: Project Execution, page 130; CompTIA Project+ Certification Exam Objectives, Domain 3.0: Project Execution, Objective 3.3: Analyze project performance by using appropriate tools and techniques, Sub-objective 3.3.2: Given a scenario, interpret the results of data analysis using appropriate tools and techniques, Knowledge of: Scatter diagrams.