Question 143 - PK0-005 discussion
During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:
A.
negotiating resources.
B.
assigning resources.
C.
assessing the resource pool.
D.
adding resources to the schedule.
Your answer:
0 comments
Sorted by
Leave a comment first