During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:

A.
negotiating resources.
Answers
A.
negotiating resources.
B.
assigning resources.
Answers
B.
assigning resources.
C.
assessing the resource pool.
Answers
C.
assessing the resource pool.
D.
adding resources to the schedule.
Answers
D.
adding resources to the schedule.
Suggested answer: C

Explanation:

Assessing the resource pool is the process of identifying and evaluating the availability, skills, and costs of the resources needed for the project. The PM reviews the SOW from the contractor to understand the scope and requirements of the project, grades the full-time equivalents' resumes to determine their qualifications and suitability for the project, evaluates the titles and salaries to estimate the budget and allocation of the resources, and estimates the number of hours for each milestone by full-time equivalents to plan the schedule and workload of the project12.