An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).

A.
Rollback plans
Answers
A.
Rollback plans
B.
Project management plan
Answers
B.
Project management plan
C.
Deployment plan
Answers
C.
Deployment plan
D.
Asset management plan
Answers
D.
Asset management plan
E.
Communication plan
Answers
E.
Communication plan
F.
Resource management plan
Answers
F.
Resource management plan
Suggested answer: A, C

Explanation:

A rollback plan is a contingency plan that describes how to revert the system to its previous state in case the change fails or causes problems. A rollback plan is important to minimize the impact of a failed change and ensure the system's availability and functionality12.

A deployment plan is a document that outlines the steps and procedures for implementing the change in the production environment. A deployment plan is important to ensure the change is executed smoothly, efficiently, and securely, and that the system meets the expected performance and quality standards34.

asked 02/10/2024
Pilocz Pi
39 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first