Question 168 - PK0-005 discussion
Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?
A.
Reviewing project blockers
B.
Defining roles and responsibilities
C.
Establishing a project schedule
D.
Determining a project budget