A project team is developing an application that will allocate a building's parking spaces. The building owner does not agree with using corporate colors in the application and has blocked the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

A.
Review of existing artifacts
Answers
A.
Review of existing artifacts
B.
Development of an issue log
Answers
B.
Development of an issue log
C.
Identification and assessment of stakeholders
Answers
C.
Identification and assessment of stakeholders
D.
Establishment of accepted communication channels
Answers
D.
Establishment of accepted communication channels
Suggested answer: C

Explanation:

The project manager should have identified and assessed the building owner as a key stakeholder in the initiation phase, and understood their expectations and requirements for the application. This would have helped to avoid the conflict over the corporate colors and the delay in testing. Stakeholder identification and assessment is an important process in the initiation phase, as it helps to define the project scope, objectives, and success criteria, and to establish a communication plan12. Reference = CompTIA Project+ PK0-005 Certification Study Guide,