Which of the following activities are performed during the closing phase? (Select three).
A.
Requesting project charter sign-off
B.
Recognizing project team efforts and rewarding team members
C.
Working with the financial team to obtain return of investment
D.
Revoking resource credentials from the system
E.
Updating the risk register with new findings
F.
Informing the functional manager about the release of resources
G.
Monitoring project team performance