Question 177 - PK0-005 discussion
During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?
A.
Obtain details from the owner of the project.
B.
Update the critical path for the project.
C.
Apply contingency reserves.
D.
Reestimate epic user stories.