Question 179 - PK0-005 discussion
During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?
A.
Issue log
B.
Scope statement
C.
Risk report
D.
Change log