List of questions
Related questions
Question 186 - PK0-005 discussion
Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?
A.
Project status report
B.
Project evaluation review
C.
Project management software
D.
Requirements traceability matrix
Your answer:
0 comments
Sorted by
Leave a comment first