A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?
A.
Ticketing system
B.
Videoconference
C.
Simple messaging system
D.
Corporate social media