Question 206 - PK0-005 discussion
A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?
A.
Escalate the change to the CCB.
B.
Review the requested change.
C.
Document the change recommendations.
D.
Validate the implementation of the requested change.