A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the best order of the stages the PM should follow to nurture the team to high performance?

A.
Forming, storming, performing, norming, adjourning
Answers
A.
Forming, storming, performing, norming, adjourning
B.
Forming, performing, storming, norming, adjourning
Answers
B.
Forming, performing, storming, norming, adjourning
C.
Forming, norming, storming, performing, adjourning
Answers
C.
Forming, norming, storming, performing, adjourning
D.
Forming, storming, norming, performing, adjourning
Answers
D.
Forming, storming, norming, performing, adjourning
Suggested answer: D

Explanation:

This is the correct order of the stages of team development according to Tuckman's model123. The forming stage is where team members first meet and get acquainted. The storming stage is where team members experience conflicts and disagreements. The norming stage is where team members resolve their differences and establish norms and rules. The performing stage is where team members work together effectively and efficiently. The adjourning stage is where team members complete the project and celebrate their achievements. Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 6: Project Team Management, p. 197; The 5 Stages of Team Development (Including Examples) | Upwork; The 5 Stages of Team Development - Teamwork; Using the Stages of Team Development | MIT Human Resources