A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?

A.
Data plan
Answers
A.
Data plan
B.
Contingency plan
Answers
B.
Contingency plan
C.
Rollback plan
Answers
C.
Rollback plan
D.
Recovery plan
Answers
D.
Recovery plan
Suggested answer: B

Explanation:

A contingency plan is a risk mitigation strategy that involves preparing alternative courses of action in case the original plan fails or encounters unexpected problems. A contingency plan can help reduce the impact of negative risks and ensure the project continuity and success. In this case, the project manager should develop a contingency plan to mitigate the risk of hurricanes affecting the implementation of the new radar system. For example, the contingency plan could include backup resources, alternative locations, emergency procedures, and communication channels in case of a hurricane. Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 7: Risk Management1; CompTIA Project+ Certification Study Guide, 3rd Edition, Chapter 7: Risk Management