ExamGecko
Home / PMI / PMP / Practice Test 23
Ask Question

PMI PMP Practice Test 23

Add to Whishlist
00:00:00
Show Answer
Report Issue   Restart test

Question 1 / 40

A project manager identified a risk on a deliverable completed by a contractor and added it to the risk register. During the last inspection meeting for the deliverable, the project manager notices that the suggested mitigation did not produce the expected results.

How should the project manager proceed?

Become a Premium Member for full access
  Unlock Premium Member